The project for the renewal of the district of La Paz is making strides.
The Governing Board today approved the first constitution and the policy agenda of the Compensation Board and the proposed development.
This means that this project has moved beyond the planning stage to begin the process of management, being closer to the start of the works that could be produced in spring.
The City Council approved in March the Special Plan to Reform Interior (PERI) of La Paz, which aims at comprehensive urban renewal district, with urban renewal, the buildings and the relocation of residents.
The June plenary gave its approval to the revised text of the amendment to the General Plan, forwarding the text to the autonomous region for approval.
The promoters of this project are the residents existing homeowners, who will return to his old house a new home at the site of La Paz.
As envisaged in the project, residents of the neighborhood will not even during the execution of works.
1,502 homes will be built 90 square meters for the owners at no cost and will rehabilitate five blocks in good condition.
The scope covers an area of 145,528 meters square, which is distributed as follows:
Public Domain
Total 115,092 m2
Clearances
53,866 m2
Equipment
9,454 m2
Pedestrian road
7,161 m2
Rolling road
44,611 m2
Private Domain
Total 30,000 m2
Rehabilitate buildings
1,341 m2
New construction
29,095 m2
Total floor area of sector
359,454 m2
Approximate capacity
2,950 homes
The rehabilitation project of The CPA provides a complete reinforcement of basic infrastructures main water supply, electricity and sanitation.
The new neighborhood will include bike lanes on major roads.
As for the management of roads, is planned as a structure "H", which will allow traffic flow inside to May Day and Fame.
The deadline for implementation of this project is ten years and will be held in five phases.
Urban obligation to ensure the simultaneous construction of houses destined for relocation of owners with housing free to use.
In addition, set the conditions for implementation of works to minimize the social impact, establishing interim measures to avoid disruption and inconvenience to nearby neighborhoods as Vistabella, La Fama, May Day and the weekly market.