Azuche 88 will carry out the renewal of measures for the conservation and protection of archaeological remains in San Esteban (31/01/2017)

Azuche 88 is the company proposed by the Contracting Bureau to carry out the renovation of the measures of conservation and protection of the archaeological remains of the Garden of St. Stephen.

This was decided at the meeting held this morning, chaired by the Councilor for Finance and Contracting, Eduardo Martinez-Oliva, which has admitted the offer presented, although he had incurred recklessness.

Finally, the project will be executed with a budget of 54,700 euros, compared to 77,000 euros of the bid amount.

The contract involves the renewal of the current conservation measures of the archaeological site and has an expected execution period of four months.

The intervention includes the superficial consolidation of archaeological structures of the deposit, the revision and reinforcement of the fences in the vertical consolidation of archaeological structures and the replacement of the geotextile mesh, as a means of direct protection against meteorological agents, as well as avoidance The development of vegetation.

Likewise, a review and reinforcement of the gravel coverage will be undertaken in the areas where the geotextile is restored and structures are repaired, as well as the filling of hollows with gravel in areas that are considered the best solution for the vertical containment of structures .

On the other hand, the works will also take into account the revision of the fence of the deposit and the review of the system of drainage of the deposit.

During all the intervention will be made with a documentary record of the state of the deposit and of the interventions that are carried out, together with the writing of a report with detailed description and the corresponding graphic documentation.

On going

Azuche 88 now has a period of 10 days to provide the necessary documentation to formalize the contract, which must be reviewed by the Contracting Bureau.

Then, the Governing Board will approve the award.

Councilor for Development, Roque Ortiz, remembers that last week was given the approval of the offers presented by the San Esteban TPP, for the drafting of the master plan of the whole of San Esteban, and OYCO, for the pedestrian conditioning of the environment, Both with a budget of 274,000 euros plus VAT.

Ortiz has expressed satisfaction that 'finally a procedure so complex that has required a lot of administrative procedures, will soon be seen.'

"We wanted to act well, with the participation of consultants and experts, with a rigorous and thorough examination of the proposals, rather than hurriedly and with errors" because we can not forget that San Esteban is going to stop being a problem to turn it into an opportunity For Murcia, which will thus have a cultural, tourism and social milestone in the heart of the city.

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information