This week the paving works for a section of Alfonso X Avenue end (04/06/2018)

The work of renovation and pedestrianization of Alfonso X el Sabio Avenue is progressing at a good pace.

According to forecasts, this week will complete the paving of the stretch between the door of the convent of Las Claras and the establishment of Orenes.

In this way, next week will begin the paving works of the existing stretch between Avenida Jaime I and the Orenes establishment.

These works will last approximately ten days.

Also, in the next few days they will start construction work on the underground containers that will be located next to the Cierva Peñafiel school and for which it will be necessary to close Santa Clara Street for one month.

The paving works correspond to phase 1A (west road from Santa Clara street to Jaime I avenue) and 1B (half of the central walk from Santa Clara street to Jaime I avenue) that will run until June 18 .

Phase 2A, corresponding to the other half of the central promenade from Gutierrez Mellado Street to the dead end street of Jesús María School, will be executed during the non-school period from June 19 to August 30 in order not to affect at the entrance and exit of the educational center.

Finally, phase 2B, which encompasses the other half of the central promenade from the dead end street of the Jesús María school side to Enrique Villar Street, will take place from August 31 to October 19.

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information