According to forecasts, on Friday normalcy will be restored in the flow of traffic |
The Department of Public Works, in collaboration with the Traffic and Public Safety, continues with the refurbishment of the underground tunnel of the Plaza de Castilla with the aim of improving road safety.
According to forecasts from Friday normalcy is restored in the circulation of traffic in the tunnel.
So we proceeded and to repair all the median curbs and has been extended and the tubular defense cleared the median.
They also have been completed repair and restoration work of drainage canal water table creating a new cross-drainage water collection water table in the driveway exit towards Murcia, which will not stagnate water.
It has also been the cleansing of the vertical panels, the placement of a steel plate 20 mm thick and repair lighting
The following work to be performed the next day, and will make the Traffic Service, will include repainting road markings, strengthening and improving vertical signs and placement of new reflector in the middle and the walls of the tunnel.
Source: Ayuntamiento de Murcia