The works of Coastal North and South facing home stretch (20/12/2013)

The Mayor and the Director of Public Works this morning signed the agreement allowing resume construction of both vials, whose investment amounts to 25.6 million euros.

Camera highlights both the impact of projects on the local economy and employment.

The new road will improve mobility and directly benefit more than 90,000 people in 14 districts

Next spring will launch the works that will virtually complete the construction of the North Coast and move permanently South Coast two high-capacity road which will improve mobility in the town and significantly reduce the traffic through the urban centers of the districts, thus improving the quality of life of its inhabitants.

Improved road communications provided for in the agreement signed this morning by the Mayor, Miguel Ángel Cámara, and the Minister of Public Works and Planning, Antonio Sevilla, which provides for the recovery of the works of both roads, the execution is altered by economic circumstances.

Saves the difficulties, it is now possible to undertake such infrastructure, in which almost 25.6 million euros will be invested.

The Mayor, Miguel Ángel Cámara, summarized in three aspects the main consequences of the development of these projects: "It will improve considerably the mobility decongest traffic existing roads and facilitate communications between the districts."

It adds Camera-continue "modernizing Murcia to give the municipality a road network of the first level."

It has also highlighted the importance of this infrastructure because in a time of crisis where governments are struggling to invest in public works, "the execution of these vials generate about a thousand jobs through collaboration between the City and the Autonomous Community, Urbamusa management. "

The actions affecting 10 sections totaling 8118 meters in length and whose execution period will be reached in most cases 14 months.

Forecasts indicate that the projects may contract in February and start work in the spring.

Specifically, 7 flights of the North Coast, with a total length of 6,019 meters and a budget of 18 million euros will be built, while the remaining three sections are in the South Coast, with a cost of 7.6 million euros and a length of 2,099 meters.

Tranches

Budget Bidding

Length

Duration of Work

Section II-CN 3.

Vial connecting Glorieta La Nora and Access UCAM-Developments

2,459,591.01

772 m.

14 months

Section II-CN 4.

Restructuring existing road access between Glorieta and UCAM-North Coast Developments in Guadeloupe

2,707,944.24

1,042 m.

11 months

Section II-CN 8.

Access-access developments north head of Torres

2,392,873.40

715 m.

14 months

Section II-CN 9.

Access north head of Torres-A4 road link

3,152,061.03

920 m.

14 months

Section II-CN 10.

A4-access link road industrial area

2,688,056.79

604 m.

14 months

Section II-CN 11.

Access Zone Industrial Developments-access-Rotonda Santomera

2,445,247.72

1,031 m.

14 months

Section II-CN 12.

Widening access road A4-A7

2,190,287.21

935 m.

14 months

Section II-CS-1-1.

Road connection between El Palmar and The Pool

2,337,088.67

569 m.

14 months

Section II-CS-1-2.

Viaduct on the A30 motorway.

Connection to access El Palmar and the South Coast

3,446,025.73

200 m.

14 months

Section II-CS-1-3.

Log in Palmar-San Ginés

1,775,214.80

1,330 m.

7 months

Total

25,594,390.60

8,118 m.

Better communications

The Coastal North and South are high capacity roads with landscaped median and bike lanes, which are designed to absorb 80,000 vehicles a day.

The projects of these roads have the following characteristics:

- Structuring Vials: Central Trunk three lanes in each direction.

In the sections of the split of Highway A-4 (Section II-CN-12) and the connection between Nora and the North Coast in Guadalupe (Sections II-CN-3 and CN-II-4), the connection is available two lanes in each direction, and the connecting sections between El Palmar and San Ginés (Section II-CS-1-3) and the stretch of road replacement RM B-3 (included in Section II-CN- 4), have one lane in each direction.

- Accessibility: Meets both pedestrian parameters fords, as the width of sidewalks, horizontal and vertical signs, and the traffic lights.

- Environment: In circular roundabouts LED lighting an increase in energy efficiency, in addition to an increase in road safety.

Bike path is included in all sections.

- Road safety: Barrier protection barrier rail vehicles and motorists in the necessary sections and wooden fences to protect pedestrians and cyclists.

- Access: all existing paths to new paths-either directly or by way of service-to leave no isolated area was incorporated.

Intersections have remained raised in the General Plan to meet present and future.

- Gardening: Artificial turf, mulberry and native species at roundabouts.

Road running

The agreement improved road communications between the municipality and the Ministry of Public Works has already allowed the opening of the Green Alternative Sangonera-in operation since April 2009 - with a total length of 3.9 km, the route runs from its link with the MU-30 freeway to the RM-603 road at the exit of the village.

That same year also opened for service on first section of the North Coast, which cross links the Avenida Juan de Borbón with Juan Carlos I (at the height of the substation Espinardo) along a length of 1.55 kilometers .

This road will have a total length of 12.06 km and will link with Javalí head of Torres Viejo, on the border with Sewell.

And from January 2010 is in the service section of the South Coast, which have a total length of 11.3 km, running from La Alberca Auditorium and Santa Catalina Highway and two years later opened to traffic road between this point and Algezares.

Since 2009 the North Coast is open for service on first section, which connects the transversely Avenida Juan de Borbón with Juan Carlos I (at the height of the substation Espinardo) along a length of 1.55 kilometers.

The nearly EUR 25.6 million in the budget has been the completion of the North Coast and South in addition to the 39.6 million already invested in the first phase of both vials and Alternative Sangonera La Verde, built and open to traffic in the previous legislature, funded under the agreement with the Autonomous Community.

The implementation of this ambitious plan to improve road infrastructure has had two immediate consequences: first, the construction of the ring road has made this may not be necessary, as was hitherto-cross the town of Murcia for displacements north to south or east to west, or vice versa, on the other, the opening of the first sections of the North Coast and South Sangonera Alternative and Green Avenue Beniaján has resulted in a substantial improvement in communications between districts .

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information